落水管圆管安装的方法
文章来源:wujian06.com 作者:瑞晨建材 更新时间:2019-06-01 18:37:05 Tag: 浏览:16
1、按照图纸标示落水管位置间隔1.5--2.0米设置固定支架;
2、管材在量取长度之后,可用钢锯、手工割锯、砂轮切割机割锯。割锯后,断面应保持平整,用钢锉除去毛边并倒角;
3、用带清洁剂的干布清洁管材外壁和内壁,去除污染物;
4、将溶解剂均匀涂于管材外壁和管件内壁,然后迅速把管材插入管件,用力旋转至少1/4圈以保证接合紧固无漏隙;
5、粘接完毕后把多余溶剂擦掉,将管材固定在位置上维持一段时间,60min内不可受外力影响;
6、待管件完全粘接后,放到设置的支架内拧紧支架固定件即安装完成。
1, according to the drawings indicating the location of the falling pipe interval of 1.5-2 .0 meters set up a fixed bracket;
2, after the length of the pipe is measured, the saw can be cut with a steel saw, a hand-cut saw, and a grinding wheel cutter. After cutting the saw, the section should be kept flat and the bristle should be removed with a steel file and the corner should be reversed;
3, clean the outer wall of the pipe and the inner wall of the pipe with a dry cloth with detergent to remove pollutants;
4, evenly coated solution on the outer wall of the pipe and the inner wall of the pipe, and then quickly inserted the pipe into the pipe, rotation at least 1/4 circle to ensure that there is no leakage gap;
5, after the adhesion is completed, the excess solvent is erased, the pipe is fixed in the position for a period of time, and the 60 min can not be affected by external forces;
6, after the pipe parts are fully bonded, put into the set bracket to tighten the bracket fixed parts to complete the installation.
2, after the length of the pipe is measured, the saw can be cut with a steel saw, a hand-cut saw, and a grinding wheel cutter. After cutting the saw, the section should be kept flat and the bristle should be removed with a steel file and the corner should be reversed;
3, clean the outer wall of the pipe and the inner wall of the pipe with a dry cloth with detergent to remove pollutants;
4, evenly coated solution on the outer wall of the pipe and the inner wall of the pipe, and then quickly inserted the pipe into the pipe, rotation at least 1/4 circle to ensure that there is no leakage gap;
5, after the adhesion is completed, the excess solvent is erased, the pipe is fixed in the position for a period of time, and the 60 min can not be affected by external forces;
6, after the pipe parts are fully bonded, put into the set bracket to tighten the bracket fixed parts to complete the installation.